📝 Cost

What Is a Sub-Meter? Sub-Metering and Cost Allocation Explained

6S Teknoloji · 08.11.2026 · 6 min read

What Is a Sub-Meter? Sub-Metering and Cost Allocation Explained — 6S Teknoloji

A sub-meter (also called a check meter) is a second meter installed after the utility's official main meter to measure the consumption of a single section of a building or facility. The utility sends one bill; sub-meters allow that bill to be fairly divided among tenants, apartments, shops or production lines. This article explains where electricity sub-meters are used, how sub-meter billing is calculated and how the common-area share is distributed, with an example.

Sub-meter versus main meter

PropertyMain (utility) meterSub-meter
OwnerDistribution companyBuilding / facility owner
BillUtility invoiceInternal invoice by building management
MeasuresThe whole facilityOne section (tenant, apartment, line)
TariffOfficial tariffUnit price derived from the main bill
SealOfficially sealedUsually unsealed, internal control

Where are sub-meters used?

  • Shop and office tenants in shopping centres and business parks
  • Apartments fed from a shared installation, caretaker flat, booster pumps in residential complexes
  • Line, department or contractor-area cost tracking in factories
  • Tenant businesses in hospitals and hotels (cafeteria, pharmacy, shop)
  • Third-party loads under one supply contract: base stations, ATMs, advertising boards

Sub-meter calculation step by step

The basic principle is to divide the main bill total by total kWh to obtain an effective unit price, then multiply each sub-meter's kWh by it. Example (figures are illustrative):

  • Main meter monthly consumption: 40,000 kWh, bill total 200,000 ₺ → effective price 5.00 ₺/kWh
  • Tenant A sub-meter: 8,000 kWh → 40,000 ₺
  • Tenant B sub-meter: 12,000 kWh → 60,000 ₺
  • Tenant C sub-meter: 15,000 kWh → 75,000 ₺
  • Sub-meter total 35,000 kWh; remaining 5,000 kWh = common areas (lighting, lifts, pumps) + metering loss

The common-area share (25,000 ₺) is distributed to tenants by floor area, kWh ratio or the key defined in the lease. Instead of the effective price, a fixed unit price written in the tenant's lease may be used; the difference between the main bill and the collected amount then stays with management.

Reconciliation: sub-meters cannot exceed the main meter

If the sum of sub-meters is larger than the main meter, something is wrong: a multiplier error, a reversed CT, a double-counted feeder or a supply that bypasses the main meter. In a healthy facility the sub-meter total is below the main meter and the gap consists of common-area consumption plus small metering loss. Track this gap every month; a sudden increase points to leakage or a fault. See main meter monitoring for details.

Choosing a sub-meter

  • Direct connection (typically 5–100 A) or CT-connected (x/5)? If CT-connected, the multiplier must be documented.
  • Modbus RTU or M-Bus communication output: essential for remote reading and automatic billing.
  • Time-of-use registers (T1-T2-T3): if the main meter is on a time-of-use tariff, the sub-meter must split the bands too.
  • Reactive registers: inductive/capacitive indexes to see each tenant's contribution to the reactive penalty.

Automating sub-meter reading and billing

Manually read sub-meters generate disputes at month end: "you misread it", "I was closed that day". The 6S Teknoloji platform reads sub-meters hourly over Modbus or M-Bus, reconciles their total against the main meter automatically, distributes the common-area share with the defined key and produces a detailed internal invoice per tenant. Because each tenant can see their own consumption chart, disputes are settled with data. See the sub-tenant billing and billing solution pages.

Related Content

Subtenant Billing — Automated PDF InvoicesMain Meter Monitoring — Time-of-UseAutomated Energy Billing — Time-of-Usecentralised energy monitoringwhat is M-Busenergy monitoring over Modbus TCPTEP (Tonne of Oil Equivalent) CalculationTHD Meaning: 5% Limit & How to Read Results

FAQ

Does a sub-meter replace the official bill?
No. The official bill is issued only from the utility's main meter. A sub-meter is an internal measurement used to allocate that bill among tenants or sections inside the building.
How is sub-meter billing calculated?
Divide the main bill total by total kWh to get the effective unit price, then multiply each sub-meter's kWh by it. The gap between the sub-meter total and the main meter is common-area consumption, distributed with the key in the lease.
What does it mean if sub-meters add up to more than the main meter?
A metering error: wrong multiplier, reversed current transformer, double-counted feeder or a supply bypassing the main meter. In a healthy facility the sub-meter total always stays below the main meter.